Phase | Process | Submitted by | Description |
Initiation | New Project Request | Customer | Public form hosted on the Facilities website for Unit employees to submit new project requests for evaluation. |
Project Creation | eB Admin | Used to notify lead PMs of project creation and forward project request form. | |
Planning | MOU Creation and Approval | Project Manager | Create MOU and send it for review and approval. Updates planned budget. |
Budget Approval | Project Manager | Used to establish the original budget, and subsequent budget changes (including net zero transfers and budget infusions). | |
Interior Design Request | Project Manager | Used to request for interior design assistance. | |
Signage and Graphics Request | Project Manager | Request for signage and graphics assistance. | |
Design | Prof Svcs Fee Proposal Request | Project Manager | Submit a task order to the contracts department in order to acquire a fee proposal from an A/E. |
Prof Svcs Contract Approval | Contract Specialist | Approval of Professional Services (ONLY) contracts after bidding/award. | |
Prof Svcs Change Order | Project Manager or A/E | Used to create a FCO Letter and Change Order for approval to modify the contract value and/or time. For professional services contract type ONLY. | |
Prof Svcs Invoices | Project Manager or A/E | Use to submit Professional Services Invoices. | |
Permit Application – Project Permit | Project Manager | Used to start the review process for a project permit. Reviewed by Building Code Services staff. | |
Permit Application – Land Disturbance Permit | Project Manager | Used to start the review process for a land disturbance permit. Required for projects exceeding 2,500 square feet of disturbance area on Mason's property. Reviewed by the Land Development staff. | |
Construction | Construction Invitation for Bid Request | Project Manager | Available after budget is approved. Used to initiate bidding for construction contracts. |
Construction Contract Approval | Contract Specialist | Approval of construction (ONLY) contracts after bidding/award. | |
Construction Schedule of Values | General Contractor or Project Manager | Used to split the contract into detailed line items for the Schedule of Values and subsequent Pay Applications. This process is only used ONCE per contract after award. | |
Construction - FCO | Project Manager or General Contractor | Pricing and approval of issues that may result in a cost impact to the project. Covers construction contracts ONLY. | |
Construction Change Order | Project Manager or General Contractor | Bundles one or several FCOs and generates a Change Order for approval to modify the contract value and/or time. An FCO must be submitted before starting the Construction Change Order. | |
Inspectors - Environmental Compliance Report | Land Development Staff | For inspectors to create environmental compliance report. | |
Inspectors - Inspection Report | Inspectors or General Contractor | Used to create project inspection reports or by GCs to request inspections. | |
Inspectors - Weekly Report | Inspector | Use to create a weekly inspection report. | |
Closeout | Project Closeout | Project Manager | Used to finalize and close out the project. Checks for submission of space database drawings, permit close-out, archives deliverables complete, and Leading 9 fund closed out (if needed). |
Archives Deliverables | Automatically started when the original budget is approved | Used to track project deliverables being sent to Archives. | |
Permit Close-Out | Automatically started when a Final Inspection Report is submitted | Used to request project permit close-out. | |
Other | Project Status Report | Create report on current status of project. Incorporates schedule and budget data. | |
Non-Prof Svcs Contract Approval | Approval of Non-Professional Services (ONLY) contracts after bidding/award. |
Was this article helpful?
That’s Great!
Thank you for your feedback
Sorry! We couldn't be helpful
Thank you for your feedback
Feedback sent
We appreciate your effort and will try to fix the article